Wednesday, April 25, 2007

The walls are going up!!!


Teams are busy install the drywall in the rooms at the Relief Center. But there is still alot of work to do.

Tuesday, April 24, 2007

Working on the plumbing


Several teams have been working on the plumbling at the Relief Center. We need help with the plumbing. If you are a plumber, we need you!!!

Working on the Sanctuary


The team from Virginia is installing the second layer of 5/8" drywall to the Chruch sanctuary.

Monday, April 23, 2007


A missions team from Virginia installing drywall at the new relief center. There is still many rooms that need drywalled.

Installing the Electric


A team from Pittsburgh was installing the wiring for the new center this week. The light and the homeruns still nedd conpleted.

Sunday, April 22, 2007

Drawing of the Relief Center



This the drawing for the new Relief Center. Click on image for a larger image.

Saturday, April 7, 2007

New Relief Center

The new Relief Center is underconstruction. It is being built by follow Christian to serve the people effected by the Hurricane. We need your help!!!